Coal gangue grinder operation:

1、Before starting coal gangue pulverizer equipment, check whether there is looseness in each connecting part, whether there is metal debris in the grinding chamber, and whether each rotating part is flexible. It shall be tested by jogging. If there is stuck or abnormal sound, it shall be immediately Stop in time to troubleshoot, when all meet the requirements, before starting the machine. After smooth operation, re-feed.

2. The feed particle size should be controlled within 12mm and the moisture content is less than 12%. If the material particle size is larger than 12mm, it should be broken before it can meet the requirements.

3, in order to prevent iron debris into the machine, should strictly test the material, it is best to configure the iron removal device in the feed port.

4. When the moisture content of the material is greater than 12%, it will affect the normal operation of the crusher and even cause an accident to plug the screen. Therefore, it must be checked whether the material moisture content is within the specified range.

5. When the coal gangue pulverizer is in normal operation, the amount of electric current should be controlled to control the feeding amount, so that the feeding is continuous and uniform. The current meter value is limited to not exceed the rated current of the motor to prevent mechanical failure due to overload.

6, after the crushed material is discharged from the lower chamber of the casing, can be used to collect or connect directly to the collection device.

7. After each crushing is over, the power of the host must be cut off. After the machine stops rotating completely, the door can be opened to check whether all the fasteners are loose or abnormally worn. At the same time, the machine is cleaned and bonded to the screen. materials.

8. Grease on the transmission part should be greased regularly.