Pulverizer operation and maintenance

May 18, 2020

 Pulverizer operation and maintenance

1. After unpacking, first carefully check whether the equipment is damaged during transportation, then put the high machine and auxiliary electronic control devices in place, and then connect the main and auxiliary machine's pipeline road. The seals are coated with "iron anchor 609" liquid sealant to ensure the tightness of the pipeline. At the same time, each stand-alone and pipeline flange are connected with a ground wire and grounded to avoid dust explosion caused by static sparks.

2. Before each stand-alone trial operation, you must check whether there are metal objects in the machine, and if there are any, remove them. Whether the bolt is firm, the tightness of the belt, the reliability of the protective cover, etc.

3. Start the motors in the following order. Turn off the damper and start. Crusher-> dust collector-> classification device-> screw feeder-> open damper-> closer.

4. After five minutes of empty vehicle operation, the operator should carefully observe the various instruments on the control cabinet and wait for the no-load current to stabilize before feeding. After feeding, the current is not allowed to exceed the rated value of 32.6A, otherwise the amount should be reduced to ensure the normal operation of the discharge electric can work regularly.

5. Stop in the following order

Spiral feeder-> after five minutes of operation, the main crusher can be stopped, dust collector, classifier-> air trap

6. The stepless shifting handle of the classifier can change the speed of the classifying wheel, and at the same time, it can achieve excellent product adjustment. If the granularity of the product is required to be fine, the rotation speed can be increased, otherwise, the rotation speed can be reduced to increase the particle size.

Maintenance

1. During the production process, the temperature rise of the bearing must be checked frequently. When the temperature rise exceeds 50 ° C, the machine should be shut down to check the cause and eliminate the fault.

2. When the new machine is running, the transmission belt is easy to extend. Pay attention to adjust the appropriate tension of the belt to ensure the working life of the belt.

3. Consumable parts should be checked frequently and replaced in time to ensure production quality and production volume.

4. Blades and bushings should be checked frequently for wear. If the productivity decreases after the wear, the particle size becomes coarser and the wear will be replaced.

5. The main engine and the graded flow bearing are grease lubricated, adopting No. 2 special grease degree 265-295.

6. The grease exchange period of the bearing is 2000 hours. The amount of grease filled is 1/2 of the space in the bearing cavity. Measure up or down. 3/4 Do not overfill with grease. Otherwise, the bearing temperature will be too high.

7. The grease changing period of the screw feeder is 4000 hours plus ordinary calcium-based grease.

Send Inquiry